How We Rebuilt a Collision-Damaged Mk4 Train in Just 2.5 Months

When a Mk4 set hit a farm trailer at 80 mph, our client lost vital fleet capacity overnight. Here's how we got it back on the mainline in record time.

months to rebuild
2.5
months to rebuild
coaches rebuilt to mainline standard
3
coaches rebuilt to mainline standard
faults on return to service
0
faults on return to service
Collision damage along the side of a Mk4 coach
Fleet rebuild

The incident

In May 2025, a passenger service formed of a Mk4 set and hauled by a Class 67 locomotive struck a loaded agricultural trailer on a user-worked level crossing. The train was travelling at around 80 mph.

The trailer became wedged on the front of the Driving Van Trailer (DVT) and was dragged for around 500 metres before the train came to a stop under braking. The train didn't derail, but the leading DVT and several passenger coaches were badly damaged. Six passengers suffered minor injuries, and the collision also damaged track, lineside equipment and a second level crossing further along the route.

For our client, the impact went beyond the damage itself. With the set out of service, fleet capacity dropped, and the risk of long-term disruption to passengers was real.

The challenge

  • Severe collision damage to the DVT and leading coaches
  • Reduced fleet capacity while the set was out of service
  • A rebuild needed quickly, and to full mainline standards
  • An opportunity to build in reliability improvements learned from years in service
Mk4 DVT on lifting jacks in the depotMk4 DVT raised on jacks during the rebuild
The DVT on lifting jacks at the depot during the rebuild.

Assessing what could be saved

On Track Group was already at the depot, rebuilding a spare Mk4 set for mainline service, when the collision happened. Because our team and facilities were in place, we could reprioritise the programme immediately rather than starting from scratch.

Our engineers stripped the crash-damaged coaches and worked alongside AtkinsRéalis to assess each vehicle and decide which could be economically repaired and which could not.

The rebuild: coach substitution and mainline standards

Rather than wait for the most badly damaged vehicles to be repaired, we selected three coaches from the spare set (the DVT, a TO and a POD) to rebuild and take their place. Each was restored to full mainline standard.

Solving the unexpected: axle removal without lifting jacks

During the first acceptance exam, we found that one of the primary springs had collapsed and become coil-bound. The train was due to move to Crewe for trial runs, but couldn't leave until the spring was replaced and the primary suspension heights were confirmed to be within specification.

There were no lifting jacks available to raise the whole vehicle, so our team developed a safe alternative. The affected coach was split from the set, the bogie was raised using two 30-tonne Hydrolyte jacks, and the axle was partially removed so the spring could be replaced.

Before any work began, every spare part was sourced and a detailed lifting procedure was written and formally approved by the Project Engineering Manager. The spring was replaced safely, the suspension heights were verified, and the train left for its trial runs.

Mk4 bogie raised on jacksBogie during the liftThe collapsed primary spring removed from the bogie
The bogie during the lift, and the collapsed primary spring that was replaced.

Reliability upgrades built in

A rebuild is a rare chance to fix the issues that have caused problems in service. Using our experience of the Mk4 fleet, we built in a range of improvements:

  • Contactor replacements
  • Control module upgrades
  • Door set-up optimisation
  • Corrosion repairs
  • Bogie lifts
  • Axle and bearing replacement
Engineers replacing an axle bearing on a Mk4 wheelsetWheelsets removed for overhaul
Axle and bearing replacement, and wheelsets removed for overhaul.

The result

  • Rebuilt in 2.5 months: exceptionally fast for the scale of work.
  • Fault-free return: the set returned to mainline service running without faults.
  • Capacity restored: passenger disruption was kept to a minimum.
  • Lasting benefits: the reliability improvements will benefit the wider Mk4 fleet.
The On Track team standing beside the rebuilt Mk4 set
The On Track team with the rebuilt set on its return to service.

What's next

With this rebuild complete, On Track is now rebuilding a second crash-damaged vehicle to expand our client's Mk4 fleet.

The project showed what On Track does best: mobilising quickly when the unexpected happens, combining accident recovery with long-term fleet improvement, and delivering complex rebuilds to mainline standards under tight deadlines.